Amber Canary gate work (A-4) slipped one week; everything else on plan.
Period: Mon 2026-08-31 to Sun 2026-09-06
Author
Priya Natarajan, SRE lead
Published
2026-09-07
Distribution
Engineering leadership, Dispatch and Integrations teams, Support leads
Previous
Week 35: Red (INC-2026-0827 outage)

Summary

Status moves from red to amber. The outage follow-ups from INC-2026-0827 are done except the relative canary gate (A-4), which slipped from 2026-09-05 to 2026-09-12 because the deploy pipeline change needed a second reviewer from the release team. Deploy volume recovered to 26 for the week and change failure rate returned to 3.8%. The one thing that needs attention this week is a decision on RFC-014's open questions by 2026-09-19; without it phase 0 misses the 2026-09-22 start.

Highlights

Metrics

Deploys to production
26
+15 vs week 35 · target ≥ 20
Change failure rate
3.8%
−14.4 pts vs week 35 · target < 5%
Dispatch API p95 latency
188 ms
−17 ms vs week 35 · target < 250 ms
Mean time to restore
22 min
1 incident (SEV-3) · target < 30 min
Open SEV-1/SEV-2 actions
1
−5 vs week 35 · target 0
Production deploys per week, weeks 29 to 36 Bars: week 29, 18; week 30, 22; week 31, 15; week 32, 27; week 33, 24; week 34, 29; week 35, 11 (deploy freeze after the outage); week 36, 26. Target 20 per week. 0 10 20 30 18 22 15 27 24 29 11 26 W29 W30 W31 W32 W33 W34 W35 W36
Deploys per weekTarget (20)
Production deploys per week, all services. Week 35 reflects the two-day deploy freeze after INC-2026-0827. Source: deploy log, query deploys-by-week.
Dispatch API p95 latency by week, milliseconds Line: week 29, 176; week 30, 181; week 31, 174; week 32, 190; week 33, 188; week 34, 198; week 35, 236; week 36, 188. Target under 250. 150 200 250 300 236 188 W29 W30 W31 W32 W33 W34 W35 W36
p95 latency (ms)Target (250 ms)
Weekly p95 for POST /v2/jobs/{id}/assign, all regions. Week 35 includes the outage window. Source: Grafana, panel Dispatch API latency.

Workstreams

WorkstreamOwnerStatusProgressNext milestone
INC-2026-0827 corrective actionsPriya N.Amber
83%
A-4 merged, 2026-09-12
RFC-014 webhook deliveryTomasz W.Green
35%
Decision, 2026-09-19
Query-plan CI check (A-5)Tomasz W.Green
15%
Snapshot pipeline, 2026-09-19
Observability: pool and queue dashboardsYuki T.Green
100%
Done 2026-09-04
PRD-024 platform review (routing provider, NFR-001)Ines F.Not started
0%
Review comments, 2026-09-16

Risks and issues

Risk or issueStatusTrendMitigationOwner
RFC-014 decision slips past 2026-09-19, pushing phase 0 into the October change-freeze windowOpenRisingReview session booked 2026-09-16; open questions assigned with dates; escalation to Ines F. on 2026-09-17 if unansweredTomasz W.
Release team review capacity delays pipeline changes (caused the A-4 slip)OpenNewAsk below; interim: platform lead granted temporary approver rights for pipeline/Priya N.
Production-sized snapshot for the query-plan CI check needs 400 GB of storage not in this quarter's budgetOpenUnchangedSampled snapshot (10% of rows, same statistics) under test; decision on full snapshot by 2026-09-19Tomasz W.
Repeat of pool exhaustion before A-4 and A-5 landClosedFallingIndex, 2 s timeout, and 80% warning shipped; risk accepted for the remaining windowPriya N.

Asks and decisions needed

  1. Answer RFC-014 questions Q1 to Q4 in the review session or in the document. Dana Okafor, Marcus Bell, Ines Fontaine, Priya Natarajan · by 2026-09-19
  2. Add a second release-team approver for pipeline/ changes, or make the temporary platform approver permanent. Head of Engineering · by 2026-09-12
  3. Approve 400 GB of snapshot storage for the query-plan CI check, or accept the sampled-snapshot approach with its known gap on skewed tables. Ines Fontaine · by 2026-09-19

Next period (week 37)

Appendix: incidents this period

IncidentSeverityDurationSummaryFollow-up
INC-2026-0903SEV-322 minReport export queue stalled after a worker deploy with a missing environment variable; no customer-facing impact beyond delayed CSV emails.Deploy template validates required variables (done 2026-09-04)
Source: incident tracker, filter opened:2026-08-31..2026-09-06.