Larkspur Systems · Platform team
Weekly status
Platform team, week 36
Amber Canary gate work (A-4) slipped one week; everything else on plan.
Period: Mon 2026-08-31 to Sun 2026-09-06
Summary
Status moves from red to amber. The outage follow-ups from INC-2026-0827 are done except the relative canary gate (A-4), which slipped from 2026-09-05 to 2026-09-12 because the deploy pipeline change needed a second reviewer from the release team. Deploy volume recovered to 26 for the week and change failure rate returned to 3.8%. The one thing that needs attention this week is a decision on RFC-014's open questions by 2026-09-19; without it phase 0 misses the 2026-09-22 start.
Highlights
- Shipped five of six INC-2026-0827 corrective actions: partial index in all four regions, 2 s pool timeout for interactive services, 80% pool warning alert, and the PR template checklist.
- Published the INC-2026-0827 RCA (v1.2) to engineering and to the two affected premium accounts through their account managers.
- RFC-014 (queue-backed webhook delivery) reached v3 with a decision log; 3 of 4 reviewers have commented.
- Reduced Dispatch API p95 latency from 205 ms to 188 ms by removing a redundant permission lookup on
POST /v2/jobs/{id}/assign. - Canary relative-latency gate (A-4) implemented and in review; not yet merged. New due date 2026-09-12.
Metrics
Deploys to production
26
+15 vs week 35 · target ≥ 20
Change failure rate
3.8%
−14.4 pts vs week 35 · target < 5%
Dispatch API p95 latency
188 ms
−17 ms vs week 35 · target < 250 ms
Mean time to restore
22 min
1 incident (SEV-3) · target < 30 min
Open SEV-1/SEV-2 actions
1
−5 vs week 35 · target 0
Deploys per weekTarget (20)
deploys-by-week.p95 latency (ms)Target (250 ms)
POST /v2/jobs/{id}/assign, all regions. Week 35 includes the outage window. Source: Grafana, panel Dispatch API latency.Workstreams
| Workstream | Owner | Status | Progress | Next milestone |
|---|---|---|---|---|
| INC-2026-0827 corrective actions | Priya N. | Amber | 83% | A-4 merged, 2026-09-12 |
| RFC-014 webhook delivery | Tomasz W. | Green | 35% | Decision, 2026-09-19 |
| Query-plan CI check (A-5) | Tomasz W. | Green | 15% | Snapshot pipeline, 2026-09-19 |
| Observability: pool and queue dashboards | Yuki T. | Green | 100% | Done 2026-09-04 |
| PRD-024 platform review (routing provider, NFR-001) | Ines F. | Not started | 0% | Review comments, 2026-09-16 |
Risks and issues
| Risk or issue | Status | Trend | Mitigation | Owner |
|---|---|---|---|---|
| RFC-014 decision slips past 2026-09-19, pushing phase 0 into the October change-freeze window | Open | Rising | Review session booked 2026-09-16; open questions assigned with dates; escalation to Ines F. on 2026-09-17 if unanswered | Tomasz W. |
| Release team review capacity delays pipeline changes (caused the A-4 slip) | Open | New | Ask below; interim: platform lead granted temporary approver rights for pipeline/ | Priya N. |
| Production-sized snapshot for the query-plan CI check needs 400 GB of storage not in this quarter's budget | Open | Unchanged | Sampled snapshot (10% of rows, same statistics) under test; decision on full snapshot by 2026-09-19 | Tomasz W. |
| Repeat of pool exhaustion before A-4 and A-5 land | Closed | Falling | Index, 2 s timeout, and 80% warning shipped; risk accepted for the remaining window | Priya N. |
Asks and decisions needed
- Answer RFC-014 questions Q1 to Q4 in the review session or in the document. Dana Okafor, Marcus Bell, Ines Fontaine, Priya Natarajan · by 2026-09-19
- Add a second release-team approver for
pipeline/changes, or make the temporary platform approver permanent. Head of Engineering · by 2026-09-12 - Approve 400 GB of snapshot storage for the query-plan CI check, or accept the sampled-snapshot approach with its known gap on skewed tables. Ines Fontaine · by 2026-09-19
Next period (week 37)
- A-4 canary relative-latency gate merged and active on all pipelines; INC-2026-0827 actions 6 of 6 done except A-5 (due 2026-10-03).
- RFC-014 review session held 2026-09-16; decision recorded by 2026-09-19; phase 0 migration PR open.
- Query-plan CI check running in advisory mode on the sampled snapshot for
dispatch-api. - Platform review comments on PRD-024 delivered to Dana Okafor.
- Status expected: green, if asks 1 and 2 are resolved.
Appendix: incidents this period
| Incident | Severity | Duration | Summary | Follow-up |
|---|---|---|---|---|
| INC-2026-0903 | SEV-3 | 22 min | Report export queue stalled after a worker deploy with a missing environment variable; no customer-facing impact beyond delayed CSV emails. | Deploy template validates required variables (done 2026-09-04) |