Larkspur Systems / Platform · Fictional example
Week 36 · August 31–September 6, 2026

Shipping again.
One gate still open.

The deploy freeze is over. The check that would have caught the outage is still in review.

At riskThe canary gate slipped to September 12.

Delivery recovered this week.

Production deploys
26
11 last week · target ≥20
Change failure rate
3.8%
18.2% last week · target <5%
Open outage actions
1 of 6
5 closed · gate remains
Production deploys, weeks 31–36Week 31: 15; 32: 27; 33: 24; 34: 29; 35: 11 during the freeze; 36: 26. Weekly target is 20.Target 20152724291126W31W32W33W34W35W36
Illustrative deploy log · W31–36 · The freeze reduced week 35 to 11 deploys.

What landed

What needs attention

The relative-latency gate is implemented but unmerged. It needed a second release-team reviewer, moving the due date from September 5 to September 12. Until it ships, the pipeline can still miss regressions that depend on data volume.

Release lead: name the second reviewer by September 9.

Priya will run the gate review on September 12. If it fails, reopen the webhook rollout date before the next update.

Next week

Validate the gate against the outage query, then decide whether webhook rollout can start on September 22. The rollout date stays tentative until that review.